Hi I'm trying to backup my primary dpm 2012 server to my secondary dpm 2012 server all files work fine except 1 agent. This one is about 1.7tb work of information and it constantly errors out saying
Recovery point creation jobs for Volume E:\(*****.####.edu) on *****.####.edu have been failing. The number of failed recovery point creation jobs = 10.
If the data source protected has some dependent data sources (like a SharePoint Farm), then click on the Error Details to view the list of dependent data sources for which recovery point creation failed. (ID 3114)
No recovery point was created, either because synchronization has not occurred since the last recovery point was created, or because no changes were found during synchronization. (ID 208)
I have tried deleting the backup job and starting it all over but it can never complete the backup
If synchronization has not occurred since the last recovery point was created, you can synchronize the replica with the protected data on the protected computer and then create a recovery point. For more information, see "How to synchronize a replica" and "How to create a recovery point" in DPM Help.